What the RFI? · Matt Brennan
Your construction project is 99% complete. The walls are painted, the flooring is down, the lights are on and everyone is talking about move-in day. So you’re basically done, right? Not even close! Getting a building ready for occupancy requires months of preparation, testing, documentation and coordination between the contractor, consultants, owner and Authority Having Jurisdiction (AHJ). In Episode 47 of What the RFI?, Matt Brennan kicks off a four-part series on construction occupancy and project closeout with a practical look at how to prepare for occupancy before the final inspection. This episode covers: When to start preparing for construction occupancy Creating and tracking a contractor occupancy checklist Architectural, mechanical and electrical closeout requirements Consultant field reviews before occupancy Schedule S-B and Schedule S-C requirements ULC fire alarm monitoring certificates Fire alarm verification Hiring and coordinating the CAN/ULC-S1001 testing coordinator Schedule C-A and Schedule C-B Letters of Assurance Coordinating consultant documentation AHJ-specific occupancy requirements Contractor testing certificates and closeout documentation Backflow testing, water testing, elevator approvals and other required reports Common paperwork issues that can delay an occupancy permit The biggest takeaway? Occupancy preparation starts months before the final inspection, not weeks. This is Part 1 of the What the RFI? Occupancy & Project Closeout series. Part 2: CAN/ULC-S1001 Integrated Systems Testing Part 3: The Occupancy Inspection Part 4: Project Closeout, Substantial Performance & Ready-for-Takeover Chapters 00:00 Ready for Occupancy? 00:39 The Occupancy & Project Closeout Series 03:43 When Should Occupancy Prep Start? 07:58 Architectural, Mechanical & Electrical Closeout 10:45 Schedule S-B & Schedule S-C 15:34 ULC Fire Alarm Monitoring Certificate 17:04 Fire Alarm Verification 18:49 Hiring the CAN/ULC-S1001 Testing Coordinator 22:33 Schedule C-A – CRP Letter of Assurance 24:09 Schedule C-B – Consultant Letters of Assurance 28:57 AHJ-Specific Occupancy Requirements 30:14 Contractor Testing & Occupancy Documents 33:20 Pulling the Occupancy Package Together 35:05 Next: CAN/ULC-S1001 Integrated Testing What the RFI? is a Construction Administration podcast covering RFIs, submittals, site instructions, change orders, field reviews, construction contracts, project closeout and the day-to-day realities of managing construction projects. Got an RFI for Matt? Send it here! 🎙️Website - WhattheRFI.com 🍏Apple Podcast - What the RFI? 🎧Spotify - What the RFI? 🎥YouTube - @WhatTheRFI
1:00:04Your project is 99% done.
1:00:07The walls are painted, the flooring is down, lights are on, and everyone is talking about move-in day.
1:00:13So we're basically done, right?
1:00:15Not even close.
1:00:17Because before anyone gets the keys, there is an entire pile of testing, certificates, letters of insurance, consultant sign offs between you and the OccamC permit.
1:00:30Today we're talking about how to get ready for OccamC, let's get into it.
1:00:38Welcome to What the RFI.
1:00:40I'm Matt Brennan and this is the podcast all about CA.
1:00:43And as you kind of guessed it from the title, the opening there, it is OccamC month.
1:00:47It has been busy.
1:00:49The month of August has been incredible.
1:00:51We've been closing off schools, wrapping them up, going for substantial, request for takeover and most important, the OccamC side.
1:00:59And it's been a halt, but we're glad we're turning those keys over to the owner.
1:01:04It's fantastic.
1:01:05And with all these projects coming in and I thought this would be the perfect time to talk about OccamC, right?