You want me to strip what? Some of the biggest financial risks on a construction project happen before the building ever gets out of the ground. In Episode 46 of What the RFI?, Matt Brennan digs into earthworks, geotechnical reports, test holes, stripping plans, and the steps architects and owners can take to reduce the risk of costly surprises underground. Because a $100,000 earthworks budget can turn into $1 million in extras remarkably quickly when actual site conditions don’t match what everyone expected. In this episode, we cover who should retain the geotechnical engineer, why a couple of test holes may not tell the whole story, when additional targeted testing makes sense, and how the civil engineer can turn geotechnical information into a stripping plan contractors can actually price. We also get into one of the most important parts of earthworks tendering: establishing unit rates before construction begins. And when excavation still goes sideways? We look at Change Directives, truck counts, quantity tracking, documentation, and the inevitable argument over whether the tendered unit rate still applies. You can’t eliminate every underground unknown. But you can do a hell of a lot more before the excavator arrives. In this episode: Geotechnical investigations and test holes Who should retain the geotechnical engineer Reducing earthworks risk before tender What a stripping plan is and why it matters Earthworks tender packages Excavation and fill unit rates Differing site conditions Change Directives for unexpected earthworks Tracking trucks and excavation quantities Reviewing earthworks extras Construction Administration during excavation Chapters 00:00 – You Want Me to Strip What? 00:29 – Welcome to What the RFI? 02:31 – Who Should Hire the Geotechnical Engineer? 05:03 – The Initial Geotechnical Investigation 08:00 – Why You Should Bring the Geotech Back 10:00 – What Is a Stripping Plan? 12:59 – Building the Earthworks Tender Package 14:00 – Why Unit Rates Matter 15:55 – Construction Starts… and Things Go Sideways 16:49 – The Emergency Site Meeting 18:26 – When It Becomes a Change Directive 20:09 – Track Every Truck 22:38 – The Unit Rate Argument 24:30 – Closing Out the Earthworks Costs 26:28 – Key Takeaways 28:23 – You Make or Lose Your Money in the Ground What the RFI? is a podcast about Construction Administration for architects, consultants, contractors, owners, and anyone trying to make construction projects run a little smoother. Got an RFI for Matt? Send it here! 🎙️Website - WhattheRFI.com 🍏Apple Podcast - What the RFI? 🎧Spotify - What the RFI? 🎥YouTube - @WhatTheRFI

Aug 172026
29 minlength
393transcript lines
Publishertranscript source

Transcript first 15 of 393 lines

1:00:04You want me to strip what?

1:00:06Today we're talking about earthworks and how you can lose your shirt before the building even gets out of the ground.

1:00:13A few test holes, a good geotechnical port, and a proper stripping plan can save you hundreds of thousands of dollars right from the get-go.

1:00:23Let's get into it.

1:00:29Welcome to What the RFI.

1:00:30I'm Matt Brennan and this is the podcast all about CA.

1:00:33If you haven't already guessed it, we're going underground.

1:00:37What I mean by that, we're going to talk about earthworks, the geotechnical reports, and stripping plans, the valley behind them.

1:00:45This is one of the biggest areas of financial risk right at the beginning of a construction project.

1:00:52You've issued for tender, you've got to award the contract, and you're ready to get going, you're exciting.

1:00:58The excavator's out there, they're moving dirt, and something happens.

1:01:02We're going to get into those details today.

1:01:05In saying that, that's where you can start with a great set of drawings, a great contractor, no issues there, even a healthy budget.

1:01:16Then you just start digging and that's when you discover the ground is not anything like you expected, period.

1:01:25Suddenly, that $100,000 earthwork budget, well, it can become a million dollars in extras right from the get-go.