Josh Dortzbach of FOREFRONT Structural Engineers on why timber gets cut at pricing, and the labor, system, and design decisions that keep it in the building. Find New Projects & Partners at the Mass Timber Group AEC Convention Grow your mass timber network. Join our newsletter
0:00SPEAKER_00You've probably seen it happen.
0:01SPEAKER_00A mass timber project gets priced, it comes back over budget, and the timber gets cut.
0:06SPEAKER_00Josh Stortzbach says that timber competes when you do three things.
0:10SPEAKER_00Know the numbers before schematic design, solve for labor, and price the whole building instead of just the frame.
0:16SPEAKER_00Josh is the co-founder and CEO of Forefront Structural Engineers, and he's got over 30 years of experience.
0:21SPEAKER_00He's also the co-founder of TMBR, a mass timber platform that connects design, manufacturing, and assembly.
0:27SPEAKER_00Forefront's work includes Intro Cleveland, which is over half a million square feet, and they're also on ninth and high in Columbus, which is set to be the tallest mass timber student housing building in the country.
0:37SPEAKER_00Here's what we cover.
0:38SPEAKER_00First, speed and labor.
0:40SPEAKER_00Fewer people are going into the trades, so what you're actually really solving for is labor.
0:45SPEAKER_00In Columbus, the install team set 12,000 square feet of mass timber every three days with a six-person crew.
0:52SPEAKER_00That matches post-tension concrete speed in Chicago, which is one of the fastest concrete markets in the country.
0:58SPEAKER_00He explains how that speed turns into real dollars through finance costs, crane time, and contractor overhead.
1:04SPEAKER_00Second, commoditization.
1:06SPEAKER_00Josh says that mass timber has to be commoditized to scale, the way 2x4s and sheet goods already are.