Podcast host Reese Tisdale is joined by Bluefield Research Director Amber Walsh and Analyst Zineb Moumen to examine the data center market through a water lens. The conversation covers what the numbers actually show, where they fall short, and what water companies stand to gain on both sides of the Atlantic. Bluefield's analysts break down U.S. and European market dynamics, address a provocative claim that the data center water problem is "fake", and share what surprised them most in the research. Key questions covered in this episode: What are the key areas Bluefield is watching in the data center market? Is the data center water problem actually "fake"—and where does that argument hold up or fall apart? What is the real problem utilities face when a data center comes to town? What are the biggest differences between the U.S. and European markets? What surprised Amber and Zineb most during their research? What should listeners watch over the next five years as the data center market evolves? If you enjoy listening to The Future of Water Podcast, please tell a friend or colleague, and if you haven’t already, please click to follow this podcast wherever you listen. If you’d like to be informed of water market news, trends, perspectives and analysis from Bluefield Research, subscribe to Waterline, our weekly newsletter published each Wednesday. Related Research & Analysis: U.S. Water Utility Strategies for the Data Center Buildout: Opportunities, Trends, and Outlook Europe Water for Data Centers: Market Trends, Opportunities, and Forecasts, 2026–2036 The Water-Power Nexus: How Data Centers are Reshaping the U.S. Water Landscape Chapters (00:00:00) - Water Fact (00:00:54) - Introduction (00:01:41) - Conversation: Amber Walsh & Zineb Moumen (00:34:09) - Wrap-Up (00:34:41) - What Caught Reese's Eye
0:00Speaker A341. That's how many data centers Texas has asked to report their water usage since 2023. This year, only 17% answered. And the penalty for staying silent? It's just a $500 fine. And that's for an industry spending hundreds of billions of dollars on infrastructure investments this year alone. But the state isn't sitting still. Texas Governor Greg Abbott just ordered utilities to make sure data center infrastructure costs don't land on regular customer bills. He's pushing data centers to adopt water reuse systems. And that's happening. But none of this really works if nobody actually knows what these facilities are using in the first place. Texas is on track to Paso. Virginia is the largest data center market in the country. So the real question isn't how much water, it's which communities are prepared and which might be caught flat footed. I am Reece Tisdol and this is the Future of Water in which you talk about all the ways which companies, utilities and people are addressing the challenges and opportunities in water. This is episode 147 and I'm pretty sure it's going to be a good one. That's because today I'm going to be joined by Amber Walsh and Zineb Momen. We're going to talk data centers, water usage, or maybe lack thereof, and the market size and opportunities for water companies going forward. There's a lot to unpack between what's happening in Europe and the U.S. but that's why I've asked Amber and Zineb join in the conversation. So let's get to that conversation and see if we can learn a little bit more. All right, so I'm joined here by Zineb Moman and Amber Walsh. Amber, Zineb, how are things? Start with you, Zineb. Where are you and what's going on?
1:56Speaker BGood afternoon, Luis, from the other side of the ocean. We are actually now at the Basela office enjoying as always, the summer vibes and very happy to be with you this morning to talk data centers.
2:09Speaker ANice. Yeah. And in fact, I will see you, I guess tomorrow because I'm flying to Barcelona tonight and then I'll join in the fun of the heat dome. Although I'm not gonna lie, it's pretty hot here in Boston, Amber, which is where you are. So what's going on with you? You're just off the back end of a fourth of July holiday. So what's up?
2:30Speaker CNot much. How are things with you?
2:32Speaker AOh, things are good, you know, just doing this and that. Good. Fourth weekend. We've got The World cup going Zinev, you've got Morocco still in it. That was exciting game.
2:44Speaker BI mean, we were expecting duone against Canada, but I'm not sure about France.
2:50Speaker ASo as I told my son last night, now it starts getting real for everybody. All right, well, let's get into it. We didn't come here to talk about the World Cup. Let's talk about data centers. So both of you are sort of fairly well entrenched in this sector. Put out some recent analysis, both in Europe as well as in the US Although in different forms. So let's just step back, I think, because it's important. There's so much noise being shared about AI data centers. So why are we even talking about data centers on a water podcast? So why don't we start with you, Amber?
3:30Speaker CYeah, that's a great question and I'd rephrase it. Why are we talking about data centers again? Because we've had a couple of chats about data centers. But it is a great question because data center water usage is ranked pretty low compared to other industries. So it's not as much a volume conversation. But it's our job to figure out what are the real opportunities worth discussing. Both in the US and globally. We see water companies like your Veolias and Ecolabs, they're calling data centers out as a key growth market. So trying to figure out what that opportunity actually is. And the industry is growing fast. We're seeing really high capex from big tech, huge announcements, hundreds of billions of dollars, greenfield builds, phased constructions. So something worth calling out is the census bureau. They put out construction, put in place values in data centers surpassed 5 billion in May. So that's up 200% since 2023. So it's definitely still growing. It's a huge market. The water piece does get complicated. As we've discussed on this podcast, companies are choosing between water based or air based cooling hybrid approaches. So it really isn't a one size fits all. And. And we're diving into to figure out what the real opportunity is.
5:06Speaker AAll right, no, I think that's super helpful. And Sineb, what about you? What's. When you look at it from the Europe side of the. Of the equation.
5:13Speaker BYeah, from the European side there are like few different angles because I mean here in the US big money burning. We got like over 6 billion plant love gigawatt corridors in Poland, solar powered in Iberia. Especially here, talking about mega compasses in Portugal, it's around 1 gigawatt, which is huge. If you compare it to other plant projects over the last five years, but also sold projects. And that's the flip side. And we got, for instance, Microsoft side in the Netherlands got public scarcity over fresh water use. We got Dublin, one of the five Club D hubs that is under a de facto moratorium. So the bottom line is the footprint is small on pa, but perception is local. It's about the tower next to door, not only the continental total and one very interesting and shifting aspect. Last year and since May, European regulators now require power use efficiency and water use efficiency reporting for operators above 500 kilowatts. So efficiency now is an entry ticket. Perception problem becomes a permitting problem. And a permitting problem is opening the water business.
6:34Speaker AAll right, so both of you said that the water footprint, at least on site's not huge. But let's pull on the thread a little bit further. What are the key areas or issues that we're watching for in the data center? So what are clients looking for? What are we sharing with them? What about you, Amber?
6:51Speaker CYeah, so we've broken it into three pillars. So definitely on site. What's happening? What's the water use? What's the cooling adoption, treatment tech, storage equipment? So what's happening on site? But then we also zoom out and look at power. So what's that? Indirect water usage from data centers. But also how is the data center disruption impacting that power sector with new natural gas plants and delayed coal retirements? So I believe last time I was on the pod, that's what we talked about. And then we are also looking at this third pillar. How is it impacting the water utilities? So the municipal landscape.
7:35Speaker AYeah, the last part's really interesting. And can we say it's the same in Europe? Zineb, are we looking at it similarly?
7:41Speaker BMore or less is similar. We unpacked three layers. So the first one on site water use with all equipment that comes with it. We got the cooling systems plus the pre treatment trains that comes with them as well. Then we got the very interesting aspects, which is the power implications since it's roughly around 75% of the water footprint. And then we got one very interesting and different aspect from us, which is the European market structure. So Europe is not one single market, but we classify it under four different archetypes that we can come back to this point later.
8:17Speaker AOkay, yeah, I want to follow up on that. That's interesting. And so one of the reasons this came up, we've been talking about data centers, but someone had sent me an article about whether the AI water Issue was fake. Right? And they were asking for my comments and so thought we'd take some time now just to kind of talk about the article, what it, what it means, and I can share this in my thread as well. But is the AI water, is it fake? I mean, is this right? What do you, what do you think, Amber?