Select Board Rewind: April 29, 2026 Meeting Update 00:00 Meeting Overview 00:17 Water Tank Updates 01:11 Resident Thanks 01:48 Case Building Bids 02:30 Housing Plan Review 02:41 Remote Town Meeting Pilot 03:11 Consent Agenda Wrap 03:32 Closing Remarks Takeaways: The April 29, 2026 meeting of the Weston Select Board featured a significant water tank update. A fruitful discussion regarding the water tank project was conducted, highlighting its progress. Tom Palmer, an outgoing Select Board member, received numerous commendations for his dedicated service. The Select Board initiated negotiations with preferred bidders for a property sale, advancing community development. A vote was cast to support a state budget amendment aimed at enhancing remote participation in town meetings. The meeting concluded with various items being approved within the consent agenda, ensuring operational continuity. The Weston Media Podcast Network is part of the Weston Media Center, Inc. We are Weston’s independent, nonprofit cable TV station and media hub and your vital community connection. Come learn, be informed, get involved, create, and contribute to the community with us! Visit Weston Media Center at westonmedia.org Copyright © Weston Media Center, Inc.
0:02Greetings and thank you for joining me for another episode of
0:05Select Board Rewind.
0:06My name is Leon Gomen and I'm the Town Manager for the town of
0:10Weston and this is an update as to what happened at the April
0:1429, 2026 meeting of the Westin Select Board.
0:19We started off with a water tank meeting.
0:22We do a monthly water tank meeting.
0:24This time it was combined with the regular select board agenda.
0:28We had a schedule update in the MEPA update where it was announced
0:32that the MEPA process for the water tank project has been successful.
0:36This refers to the land swap issues that the state had to review.
0:43It now will go to the legislature for their review and
0:46approval.
0:47They also Talked about the 60% design and where that stands in the