Navigating Major Programmes · Riccardo Cosentino, Shormila Chatterjee, and Evgenia Jilina
How do we finance nuclear power plants in Canada? In this episode, Riccardo applies his experience financing large infrastructure projects to a deep-dive discussion with Chris Keefer. The Toronto physician and the President of Canadians for Nuclear Energy has excellent questions about the renaissance of this energy source and the process of funding these vast, costly, and promising initiatives. Riccardo explains why nuclear has historically depended on sovereign balance sheets, public utilities, and government-backed financing—and why the long-tail construction risk of the sector makes private lenders wary. The conversation compares nuclear to other major infrastructure and energy assets, from hydroelectric projects and bridges to combined-cycle gas turbines. Along the way, Chris and Riccardo unpack key financing concepts and why construction certainty is such a major determinant of cost of capital. The discussion explores existing projects, such as Hinkley Point C, Sizewell C, the Thames Tideway Tunnel, and Ontario’s nuclear context to show how risk is assigned, priced, and sometimes pushed back onto governments or ratepayers. Ultimately, the episode highlights that there is no universally good or bad financing model. The right structure depends on policy objectives, owner capability, risk appetite, market conditions, and whether the project can attract private capital without driving up the long-term cost of electricity. For Ontario and other jurisdictions considering new nuclear, the central challenge is not simply whether to use public or private money, but how to bring the right capital into the project while keeping the cost of that capital low. Key takeaways Why public interest infrastructure often requires more than a simple public-versus-private financing debate The benefits of public-sector or sovereign-backed financing for nuclear projects; Why transferring risk to the private sector can make electricity more expensive; What select UK nuclear power plants reveal about different nuclear financing models; Why Ontario’s experienced nuclear owner position may shape how future projects are financed. Quote: “Project finance is asset-agnostic." -Riccardo Cosentino The conversation doesn’t stop here—connect and converse with our community via LinkedIn: Follow Navigating Major Programmes: https://www.linkedin.com/company/navigating-major-programmes/ Read Riccardo’s latest at www.riccardocosentino.com Follow Riccardo Cosentino: https://www.linkedin.com/in/cosentinoriccardo/ Follow Chris Keefer: https://www.linkedin.com/in/chris-keefer-md-166a3698/
RICCARDO: The premise that the private sector can do it better and the private sector will generate better outcomes. That premise is no longer valid because evidence tells you otherwise. So then why are you paying a premium to get private capital if the benefit that private capital bring is actually not there? RICCARDO: You're listening to Navigating Major Programs home to the conversation Elevating the Infrastructure Industry. I'm Riccardo Cosentino. EVGENIA: And I'm Evgenia Jelena. SHORMILA: And I'm Shormila Chatterjee. And together we'll press the industry's experts on the complexity of megaproject management, emerging artificial intelligence, and the critical leadership required to approach these multi billion dollar projects. EVGENIA: Let's see where the conversation takes us. RICCARDO: At the Canada Nuclear association conference you in April 2026, I had the pleasure of chatting with Dr. Chris Kiefer, President of Canadian for Nuclear Energy. For his advocacy, he has led a turnaround in Canadian policy on nuclear energy with successful campaigns to life extend nuclear power station and include nuclear energy within green financing mechanism. We decided to continue that conversation on the podcast Asking the Big Question how do we finance nuclear power plants in Canada? Although I'm a civil engineer by trade, in the last 25 years I've focused a lot on investing and financing large infrastructure projects. Nuclear is not currently in my portfolio and yet given my company roles as the steward of Canduk technology and the Giver renaissance, I've now started to apply what I know about farm finance large complex project to the nuclear industry. We start this conversation with Chris leading the discussion about the historical context of financing nuclear projects. Chris: Big challenge. I mean historically uh, you know, we've funded nuclear power plants and um, other large infrastructure very much through the public sector, through uh, public debt. That's certainly changed over the years. I'll um, let you kind of decide on uh, how you want to get started. I've given you a few threads to tug on there in terms of again some comparisons to other technologies and the history. RICCARDO: I mean. Well, let's start with why historically our uh, nuclear power plant has been financed for, through what I call sovereign uh, balance sheets of public sector financing. Or you know basically the, either the state utility or the utilities which is typically owned like if you look at opg, yeah it is a uh, is a crown corporation, but it's really a child of the province of Ontario. So when they, they finance project uh, it's really sovereign, sovereign debt for the province of Ontario. And, and the reason being is the risk. I mean why, why uh, do you have to use why? I think that the Reasons are two actually. One is risk. The long tail risk of nuclear project, uh, and the history of nuclear, of delivering nuclear projects. That scares away uh, private sector lenders, private equity, private debt. And the other one is obviously, I think you say it many times on your podcast, one of the biggest costs on a new nuclear power plant is interest cost. So obviously you want to minimize the interest cost. And it's well established that public sector entities can borrow money at a cheaper rate than the private sector. It's a given. And that is if you want to do a little bit of uh, Finance 101 is because uh, sovereign, so state provinces, even municipalities have the ability to tax. And so that gives a lot of comfort to lenders, that being debt or equity to lend to those entity because they know that if something was to go wrong, I mean they have an ability to raise more money through taxation. Private sector entities, they need to raise more money for more profitability. And that's not always in the full control of the, of that particular entity while taxation it is in the full control of the public sector. Chris: And when you have like a large um, regulated monopoly, uh, private utility in a sense, they kind of have taxpayers, those are the ratepayers, they have a base upon which they can draw, they can increase price, they can pay back whatever debt they've taken on. So they often I guess get lumped into that similar basket. And you know, just for sake of comparison when we're talking about public versus private debt, can you give us like some numbers here in terms of interest rates? I know those are also going to change based upon the prevailing kind of macroeconomic environment. But what kind of differences are we seeing? RICCARDO: I mean again it's all related to risk. So the way that typically the interest rates are calculated, and so this is, you look at your bank loan is typically the government, in our case the Government of Canada 30 year bond, that's sort of the risk free instrument and then that's basically the overnight interest rate. So between banks. So that's sort of the floor and that's typically dictated by the monetary policy. You print more money, you got inflation. And so there's supply and demand, supply and demand of capital that uh, makes that overnight rate fluctuate and the 30 year bond fluctuate and everything is priced off that because obviously you take, you know, the cost of, the cost of capital is you take your risk free capital, never risk free, but you know, the, the most risk free is the 30 year government of Canada uh, bond because that's the safest Investment, so that's considered the risk free. And then everything else is calculated on top of that as a spread to that number. So as that number fluctuates. So you never talk about the interest rate when you, when you're pricing uh, finance instruments, you're always talking about the spread over the interest, uh, uh, the risk free uh, tool they use for that particular country. And then you know, that spread increases as the risk increases. I don't think you can have an absolute number of what the interests are. But like as you can imagine, you know, and it's also the risk of the corporation. But when we're looking at uh, uh, nuclear project risk and the financing on nuclear project is the risk of the project. So not so much of the, I mean the entity obviously that backs the project, but also the risk in project itself. And when you looking at project finance versus corporate finance that you're introducing another degree uh, of um, complexity. Because now in a project finance is also called limited recourse finance. There is no recourse to any parent company. And if you want we can try to unpack that a little bit because I think it's an important concept. And so, you know, if we think of corporate finance is what a corporation does to raise money so they pledge their assets. So if you say you uh, you know, akin realis, you have office buildings, you know, you have physical assets that you can pledge, or if you want to keep it even simpler, your mortgage, you're pledging the property that you buy. So if you don't, if you don't repay that mortgage, somebody comes and repossess your house and that's how they make all the debt. Project finance, uh, there are limited assets and there's also no recourse to any entity. So the equity that is invested, that gives ownership to that particular project is the only amount of capital that can be repossessed by the lenders if the project doesn't get completed. So obviously, you know, when lenders lend is they have an expectation that the plant in this particular case get to cod, you start producing electricity, you start to generate revenues, and that revenue allows you to repay the loan that you borrowed. And obviously if there are cost overruns or there are other issues, you know, there are cushions in the equity, uh, there are cushions in financial cushions in the project that allows to absorb some uh, shocks. But if it's a true no recourse or limited recourse finance, there is no recourse to anybody else. While if it's a corporate loan, if it's corporate finance. You know, they can, uh, the lenders can go and repossess the company. They can take over the company. And the company obviously is a going concern. And they have, and they have assets. And if, you know, if you're, you know, if you are, you know, a car manufacturer, they repossess your plant or they repossess your, Your inventory. And that's all collateral. A power project doesn't really have collateral apart from what has been built and the equity that is, is being injected. Chris: And if it doesn't get built, then that's a, That's a major problem. Uh, RICCARDO: yes. Or if he's extremely late. Chris: Right. Well, again, I think, uh, having a sense of historically how this has played out and what we've seen recently, we have a number of projects really, you know, we have kind of one reactor that's been built a number of times now in serial and Europe, um, in a couple of different environments. Um, and it's been really interesting, you know, who's left holding the bag. Several of those projects are done now. Uh, Flamonville, I always mess up the Finnish pronunciation or something like this. And we have Hinkley Point. Now we're on to sizable seat. I think, you know, comparing those projects is, is very interesting, uh, because it seems like with. With Flamonville, this is a, uh, you know, French project, uh, edf. This seems to be our sort of traditional way of financing projects with sovereign debt, low cost of capital. You know, the way things are done maybe in. One might refer to as the good old days here in Ontario or in other sort of, I guess state, uh, led nuclear programs. I guess there was an export fixed, uh, price contract offered to the Finns. Obviously was, uh, not an easy build, but the Fins seem to be happy with it. All of the risk, in terms of what you were saying before, like who. Who carries the risk was, you know, the French. Once again, God bless the French. The Fins are, you know, maybe a little testy, uh, because their electricity came five years late or whatever it was. But, uh, they didn't, they didn't get hit with huge bills. Um, and then we have Hinkley Points, which is uh, a really different model. And I think it probably speaks a little bit to uh, uh, some of the great things that have come out of the UK and the not so great things Dereg. Deregulated electricity markets and PFI private finance initiatives. So maybe let's just illustrate that transition from um, I guess more public debt, sovereign debt financing towards what uh, we saw at uh, Hinkley Point. RICCARDO: So I think, yeah, the PFI Private Financial Initiative I think is an interesting and I can give a bit of a history on that. And that was started in the 90s I believe of John Major, that pushed uh, PFI and it was a way to obviously get private capital. But back then they were able to put these assets off balance sheet, meaning that because they were using private sector financing, it wouldn't show up their investment. That project and at the time used to be mostly hospital, courthouses, prisons, highways. And so those assets, there's uh, an accounting rule that those assets, if they were done for a pfi, they would not show up on the government books. And so that obviously was very advantageous because that means that you can, you can use the private capital to build those assets and then you, you keep the fiscal capacity or the borrowing capacity to borrow to do other things, you know, social programs or you know, other public, public sector initiatives. Obviously that changed in the night. Um, they changed the country rule because they, I think we have to run that to review and, and, and, and they had to take a more cautious approach with accounting. So you know, PFI Private financial initiative and PPPs, we're familiar with them in Ontario. They are uh, they're using, yeah, they're using private capital, but they're not off the government balance sheet because the liability of their assets stays with the government. So that benefit that was there when it first started of keeping off your book so you have more borrowing capacity kind of went away. And, and then it became really a uh, a uh, tool to attract. You know, there was a feeling that, you know, the private sector can do it better. The private, you know, you want to tap into the innovation of the private sector so you want to transfer risk and by transferring risk you, you know, you're rewarding that risk transfer for, with a higher profit for the private sector. If they're able to deploy the ingenuity and create a better outcome for the institutions or for the government, uh, that is procuring that infrastructure. I mean that thinking is kind of evolved and that's why you see, you, you know, see less and less of PPP pfi, you know, uh, the, even the risk transfer concept has fallen out. Where you know, if you look at you, you know, from listener familiar with the nmp, you know that that is more of an IPD alliance type contract between, between the parties. And that seems to be in the infrastructure space where I predominantly operate. You know, contractor won't take fixed price risk anymore. They expect a uh, more Collaborative approach. So the, the paradigm is a shifter where yes, you want private sector involvement and you want, you want their ingenuity, but transferring the risk is either not palatable, expensive or doesn't actually produces the outcome that you expect to be produced. Chris: So, so time traveling back to John Major's prime ministership or that era, very kind of neol era. Um, you know, if you have a government that wants to be lean, wants to cut taxes, still is required to build infrastructure and provide services and hospitals and whatever else, this is a way I guess maybe to kind of kick the can down the road because you don't need to issue huge amounts of public debt and face, you know, an examination by the opposition party or by the media. Um, you get private enterprise to do this, but someone has to pay the bill at the end of the day. And from what I understand, you know, you'd get these private entities, uh, maybe spinning up joint ventures to you know, borrow the capital to get the project going and then the government has got to pay back. I guess it's a bit like a mortgage. Rather than loaning the money itself and doing it with a very low cost of capital, they get to avoid, you know, putting a big lump sum on the books, but you got to keep paying for it. So go, go into that a little bit with us in terms of how that maybe started to catch up, you know, as the experiment unfolded. RICCARDO: Yeah, I think, I think we need to draw distinctions between availability transaction and revenue transaction. So power plants typically are ah, considered revenue transactions because ultimately you only get paid if you generate in the electricity. A ah, toll road is a revenue transaction because you only get paid if people use your, your, your highway train to a certain extent are also the same though highly subsidized. So that trains is a slightly different uh, but airport is another asset class that is revenue based where you're landing charges and that you can bank on that to repay whatever you're borrowing. When we're talking about social infrastructure, your hospital, your courthouses, even highways that don't have toll road the repayment. So if somebody borrows money to build it, the repayment happens if the asset is available. So you're no longer taking volume risk, so you're no longer responsible for attracting new customers for you know, finding consumers that use your asset. You just as long as the, you know, take a hospital, your doctor, you know, as long as the hospital is probably maintained, the elevators are working, you get your payment. If the elevators are not working, you're getting a penalty. So you're Receiving less money. So that's the incentivization mechanism. But ultimately you're not taking the volume risk. So if a patient doesn't show up at the hospital, you still get paid? Well, in my case I don't, but RICCARDO: power plants are different. Power plants are different, yeah. Chris: Right, Right. So let's I guess dive into Hinckley Point then, because this is uh, I guess the seminal example. It's not actually a PFI from what I understand, but it's sort of sticking true to the philosophy of one. RICCARDO: Yes. Chris: So tell us about the finance arrangement that was reached there. The why. Like again, I love getting in the time capsule and just trying to understand why people made the decisions they did when they did. And I might make a case as to why. I think it was actually a good idea. But let me try and understand it better first. You, you explained to me. RICCARDO: Yeah, so I think it was a desire from the UK government and you know, I don't recall exactly so which government was it? But it was probably, probably um, Conservative government that pushed that because they wanted a model where the private sector was taking all the risk. That was the policy objective I believe is the private sector needs to take the completion risk and the operation risk. However, there was a challenge with the revenue model used because as we talked about it, you uh, need to make sure that EDF in this case is going to be able to repay to have return. So they need to guarantee that the electricity will be bought and will be bought at a certain price. So typically for normal power plants you have power purchase agreement PPAs that basically you can take to a bank and say well, a commitment for my electrons and so you can lend me the money because once I get to cod, I gonna get revenues guarantee. In the UK they use contract for difference, which is uh, well established mechanism, uh, that was used for offshore wind and onshore wind. And that's basically because the price of electricity fluctuate. Obviously the borrower cannot have that fluctuation. They need to have predictability in their revenues. So the contract for difference was put in place with a strike price. And basically it's almost like an insurance product where whatever the market price of electricity is, the producer will always receive the strike price and the difference, uh, if the market is lower than the strike price is filled by the government and if it's higher, the benefit is shared back to the government. That will be a two way contract for difference. But fundamentally the UK government wanted somebody that would develop the project, build the project, run the project and take all of the risk. And basically the strike price that was negotiated at the beginning of the project. Basically the strike price is supposed to cover all your costs. So you take all the assumed costs up to COD and obviously your operating cost as well. You then discount it back to a net present value and you basically have the amount of cost that you have and then you divide it by the amount of electricity you're going to sell and that's your strike price. And plus your profitability, everything is accounted and you got your strike price. So that's perfect if all those assumptions that you made on day one hold true. Chris: And the strike price in this case, M EDF I guess made a case that it should be fairly high. I believe it was £92 and 50 pence. I think they still use pence in the UK. RICCARDO: Yes, they do. Chris: Um, and I guess inflation adjusts up now. I think it's 127 pounds per megawatt hour. Uh, that ain't cheap. Um, and so they were pricing in a fair amount of risk. And from what I understand from our earlier conversations, it's interesting because EDF is, you know, basically a sovereign backed crown or state entity, but, um, they're considered to be private equity in this, in this case. RICCARDO: Yes. Chris: And so, you know, we talk about sort of the dynamism of, of the private sector here. It was the French and the Chinese as well. Right. The uh, cgn, China Nuclear Group, I forget the exact acronym, but who basically they become, is it 100% equity owners of the station in terms of again, taking on the construction risk, owning it, and they're just going to get paid the strike price for 60 years, 80 years, and they've negotiated it high enough such that they're probably anticipating this is a nuclear project. There's some risks, there's decent risk, it'll go a little over. Um, so we're going to build in this contingency into our contract for different strike price. There's probably a lot of controversy and I guess this is different than Oikoloto where I was like fixed price. I think from what I understand Finn's, you know, we're so confident, um, we're going to build you a power plant and uh, and sign it over to you. This was a little different, but in the end what is interesting is, yes, it was a high price, but I mean, Hinkley is gone crazy. RICCARDO: No, if you ask EDF right now, no, their strike price was not high enough. Chris: Right, exactly. And so they have eaten the risk. Right? I mean, yes, they kind of the Brits kind of sold their, sold their souls or something. I'm not sure what the right, right saying is here. Uh, but in the end they didn't get as good as the fins, but they could have got it worse I guess. So would that be an argument for this model? Because I know size will say they're taking a different tack. RICCARDO: Again, depends which hat you're wearing. Right. I mean I think despite the strike price being high, I think the British user ratepayers got an amazing deal like from, from what I hear, I, uh, mean you know, the, the equity investment has gone down to zero for EDF or you know, it's certainly not what it was supposed to be be. Chris: Which means, what does that mean? The equity investment going. RICCARDO: So they, they wipe, they wiped out their investment. They're never going to make any money. Wow, they've lost. So let's say you have to put, you know, let's say you buy, you lost. If you think in, in a, in a, ah, mortgage, um, context you lost your down payment, you put in the money and the down payment is gone, you're never going to see it back. So you, They've lost their equity investment. I mean we're talking. Chris: But they still get to live in the home, right? They still get to run the power plant and earn that strike price. But the strike price, y. I wish, RICCARDO: I wish they would like to, I think they want to move out to be honest, but they can't. But they can't move out. They got to keep their house going even though it's costing them money every day that they do. Uh, and they never going to see a penny back. Chris: So basically they're saddled with, so they've taken on so much debt even though they were probably able to get finance at a lower cost because they're a state company essentially. This is something else I don't really get. So they're borrowing, let's just make up some numbers. Let's say EDF, uh, is borrowing at like 3 interest to then loan or provide this capital to the British uh, to get this project going. Even um, though their cost of capital is low, the strike price has not been high enough given the cost overruns for them to be able to service that debt and make money off of it. It's all just going to disappear into, into trying to service all of that debt they took on. RICCARDO: and some of it has gone into the cost overruns because obviously if you, you know, if you're assuming that the project is going to cost a Hundred, you're going to put a, you're going to go and buy and take $100. Sorry it's going to be a hundred dollars plus your profit. Right. And the profit is now gone. And in fact it's more than that. The hundred dollars is no longer enough. They had to put more money. And that money that goes in is never going to make any money, any profit. So they're sinking good money after bad, if you want to say it that way. And they have to, they don't have a choice. They can't walk away. So even though they know that every dollar, every pound they put in is never going to generate any profit, they have to keep putting it in to finish the project. Chris: and at least it will pay down some of the debt. You're saying it's not enough to pay off all of the debt they've taken on but they couldn't walk away like Santee Cooper did with VC Summer because they've sunk just so much capital. Is they need to have some sort of revenue stream to pay back 75% say of the total debt. They'll never pay back 100% of it. RICCARDO: I mean Inkley is actually an interesting one because it's 100% equity. So there is no, typically you, I think there is some, some export development credit from France but the majority of it is, is, is, is EDF money and so, and obviously given to them probably by. Well EDF is a large corporation so they're, they, you know they're, but they're state backed so EDF will never uh, and it's like opg, you know, they'll never go bankrupt no matter what happens because they're an entity or the, or the state. So the state will always step in to fix it's too big to fail kind of thing. So they invested the equity, they've used the equities to fund construction. They were expecting as I said, to only invest a hundred dollars of equity, 100 pounds of equity and then what they ended up doing is putting double that in. But the new money that went in was never going to generate any profit. So you can imagine for a private sector entity to disburse cash for an initiative that is actually not going to return anything. It's very, very, very painful. Mhm. Chris: I'm wondering over what timeline uh these financial calculations happen because you know, with a nuclear hydro asset we're talking, you know, I think very conservatively 60 years, more likely 80 possibly and maybe even probably 100 years of operation. Not maybe you can explain Discount rates briefly to me because I feel like I've read about it 20 times and I still struggle slightly. But how does that work with such a long lived asset? Like surely, okay, if the French get to own this thing for 60, 70, 80 years in the year 2070, they're going to be sitting pretty happy again? RICCARDO: No. Chris: Or are they still going to be? No, not even? RICCARDO: no, because the modeling, so when you come up with a strike price, you have already taken into account that you're going to have that asset for 60 years. It's already built in. Everything is. Chris: So the modeling is based on 60 years. It's not, not like a. Okay. Wow. RICCARDO: No, no, yeah, it's, it's everything because these are concessions. Right. So you typically get a concession. Right. And you specified in the contract for how long you're gonna have. So if you're in Toronto. The 407. Yeah, the 407 is and it's, it's a 99 year lease. So it was awarded in 1999 to a consortium but eventually the Highway 407 will revert back to the government, um, probably 85 years from now. Um, whatever. I can't do math, although I'm a number person, I can't do math in my head but yeah, so everything is taken into account. So the, the life of the asset has been taken into account. Everything is accounted for. Everything is accounted because it's ah, a, it's project finance. So it's standalone. Everything needs to make sense on a standalone basis. Chris: Yeah, I mean I've just heard that uh, often these financial calculations are made as if the asset's not a nuclear plant doesn't have quite as much life as it has. And maybe it was made for 60 years and the asset is going to live 100. So maybe there is a 40 year buffer. But based upon discount rates in the time value of money, that means, you know, it's not much comfort to uh, you know, the French in 2026. RICCARDO: Yeah. And I mean as I said, typically the agreements tell the operator for how long they're going to have the plant and that's what they account for. But the discount rate, the way I explain discount rate is would you rather have a dollar today or a dollar tomorrow? And so a dollar today is always going to be more valuable than a promise of a dollar tomorrow. And so the difference between that value is time value money. And that's the concept is time value money. And so then the difference between the value of a dollar today and a dollar tomorrow is the Risk is the cost of the risk associated of not receiving the dollar tomorrow. Chris: Okay, so if I tie my money. RICCARDO: Confused you? Chris: No, no. I mean, I guess, I guess every lender is going to have a different tolerance of risk in there and thus a slightly different discount rate. And then that's ultimately going to determine the conditions that they demand and the interest rates that they ask for. And maybe uh, if we just go on to just the debt, not the equity side, but the debt side of things here. That is why private lenders, they have a higher discount rate, like a lower tolerance for risk because they can't go crying to mommy and daddy, you know, taxpayer, and get bailed out. RICCARDO: Yeah. And also that's my money and your money they're playing with. Right. So as a, as a, as a credit, as a customer of the bank, that's what the bank uses is my deposit and your deposit. So they have to pay their deposit back so to us eventually. So they obviously don't want to take big risk with those investments. And then uh, unfortunately nuclear is being label as extremely risky. And so you know there are regulations that actually prevent just lending, lending money to nuclear without guarantees that that money is going to pay back. Because the history doesn't help the history nuclear project doesn't help convincing somebody. Don't worry, it's going to be, this time it's going to be fine. So you can land and so the debt is available. But when we look at uh, you know, export credit plays a big part, you know, because this is a big, big project and countries want to export their services, their products and so export credit plays a part. And then with expo credit comes the guarantee associated. However, that guarantee is also needed for the debt that is not part of the export credit. So if you're borrowing money, some sovereign entity needs to guarantee that that money is going to be paid back. So no commercial bank will lend into a nuclear project without a sovereign guarantee. This is going to be a repayment. And some of the sovereign guarantee comes for the export development agency that is lending the money or it comes from the host uh, government that is uh, hosting the country that is hosting that plant. Chris: I think it's um, illustrative to um, look to the combined cycle gas turbine industry as what we would love nuclear to be. Um, in terms of quick construction project, one that's very predictable, one with a cadence of 100 units a year, really well established supply chain, a lot of price certainty, highly modular, made in factories, uh, yeah, something that can return investment very quickly and um, turn around and start producing power in 18 to 30 months or something like that. And that's why I guess these combined cycle gas turbines are offered as fixed price by the vendors and why they're typically financed by private debt and equity. RICCARDO: Yeah, um, yeah. And then like if you. So I sincerely. We use, we used to uh, develop finance large uh, combined cycle power plant. In fact in my portfolio I still have one that we built in Algeria is a combined cycle power plant uh, that we are still operating and maintaining and we have an investment in. And yeah, and again this is go back to the project finance. Right. So because it's predictable, if I want to finance uh a uh, power plant, a uh combined cycle power plant, all I need is a commitment for somebody to buy my electricity at the back end. And I need a contractor that is guarantee a fixed uh, price date, certain outcome. And based on two those things, I mean I'm simplifying but based on those two things I can go borrow the money because if the contractor is reputable, obviously the lenders do uh, due diligence on that contractor. But if the contractor is reputable they have experience, they can demonstrate experience. That's good enough in itself. And also the contractor puts up guarantees for that fixed price. So it's not just a promise for a fixed price. Uh there are liquid security parental guarantees that the project developer can, if the contractor doesn't complete, can take that liquidity the extra and uh, those guarantees step in and finish the project. The lenders can also do that. You know, if everything fails the lender can come in and finish the project. That's a typical thing on um, on limited recourse financing that there are stepping rights and there is liquidity in the project to complete if things go wrong. So it's actually quite simple. Uh, and, and so you could replicate that in the nuclear sector if you could have the construction certainty. Because I think the PPA and the you know, the back end revenue is, that's not a problem. You know the problem is the certainty in the construction. Nobody can guarantee the on time completion of the plant for a fixed price. Nobody. And I'm not a nuclear engineer and not in the nuclear sector. I'm um, scratching my head why that can be. But clearly as a society we haven't quite figured it out. How can we do that? Chris: Well, and yeah, and to be charitable to the small modular reactor paradigm which I'm often critical of, I mean I think that's one of the real goals there is again to try and be more like combined cyclic gas Turbines have an, um, economy of multiples that, again, provides that certainty when you're organizing a project, you know, what is my steam generator cost? Oh, well, we make, you know, 20 of these a year and, you know, put them in this plant a month ago. And that's what it costs. So you have a clear sense of things. We just do not have that in nuclear because we're not doing enough projects and really big components by nature. Um, you're not banging out high volumes of them. So I think, like, uh, my earliest days as a nuclear advocate, I remember someone saying, like, don't. Don't think of a nuclear power plant as a power plant. Think of it as an airport or bridge. Right. And so government has financed these things in the past. I mean, if you think about, you know, the French response to the, uh, 1970s oil, uh, crisis, you know, this was a matter of strategic importance and national priority. You know, they used a lot of oil for power generation. And France at the time had solid colonial relationships with Algiers and other places. And, uh, yeah, they needed to make a switch really fast. So they didn't re. I mean, it was just a whole other consideration when you're thinking about, you know, financing infrastructure. So I don't know if, like, if. If you're in your. In your portfolio, you've also, you know, been financing bridges or other things like that, but draw some comparisons. I guess. In that world, we've come. We've compared to a combined cycle gas turbine, and the comparison is not very favorable. So in terms of, uh, finance. Yeah. What are the mechanisms that play with, say, a huge bridge? RICCARDO: I mean, to be honest, it's all the same, right? Finance, it's. I always say that, uh, project finance is asset agnostic, aside from the construction risk. M is really asset agnostic. I mean, it's infrastructure. So I do have a bridge, for example. Chris: If it's not a toll bridge and maybe like, like you're not getting revenue back, the state's doing it because it says, hey, this is going to bring value. It's going to connect these two places. It's going to generate economic vibrancy that maybe trickle back in terms of taxes on increased economic activity. But. RICCARDO: But that's why this. I think large infrastructure is divided into categories, social and economic. Okay, Right. I think social would be your buildings, your hospital, your courthouses, your prison. That social infrastructure, economic infrastructure is bridges. And the. And. But you could. Again, I have a bridge. I can tell this story. Like in my portfolio I have the Champlain Bridge. So we built The Champlain Bridge is a design, build, finance, maintain and operate. And that's a bridge in Montreal. It's a beautiful, beautiful new bridge that we built. And when we bid that job, that was under the Harper government and the RFP was actually a toll bridge. So we were supposed to bid for a toll bridge. However, they didn't transfer the revenue risk. Again, there are different models for different objectives. And so even if you take the other bridge, the one that you see in the press every day, the Detroit river crossing, I also built that big bridge and that is a tall bridge. But again, the concessionaire, uh, the government said we don't want you to take revenue risk, so we will make sure that people use it. You just have to collect the tolls, give it the tolls to us. And as long as you do what the contract says, you will get paid. But that's a policy decision. They could have very easily also transferred the revenue risk and say it's your job if you do it. Like the 4 7. The 407 is the classic where the revenue risk was transferred if people don't use the 407. Atkins Realis, uh, when we were an investor, we would not get as much dividend. So we had an incentive to make sure that people would use the highway. If you're just getting an availability, the government needs to make sure that people use the highway. And the reason you transfer revenue risk or you don't transfer revenue risk is really again, cost of capital. If you want to keep your cost of capital down, you don't transfer the revenue risk more and more. I mean, as you know, in Ontario, apart from there are no other toll roads, there's no political appetite for toll roads in Ontario. But ultimately it's the same thing. You could have a power plant, I mean, where the revenue risk, I mean to a certain extent the OPG power plant, the revenue risk is with the government. Right. I mean they need to produce. If you are uh, uh, a, uh, Bruce power, the revenue risk is with a private sector because it's a private sector entity that is responsible for generating revenues. I don't think there's a good model or a bad model. It really depends on the policy objective and what you're trying to achieve achieve. You know, and if you want to draw it back to nuclear, I mean, if you want to transfer the risk. So if you want, you know, if you. Again, the UK government during income negotiations, I want to transfer it. I don't want to be burdened with the risk associated with cost overruns. Chris: Right? RICCARDO: You transfer it. Obviously the cost of electricity is going to be high. So you're trading off a uh, low cost of capital and therefore a low cost of electricity for the revenue risk transfer. For the. Sorry. For the risk transfer. Chris: And, and so far, I mean if, if the plant hasn't produced any power yet, the UK government and ratepayer. I mean this whole drama means nothing so far. They haven't lost a cent yet. It's a great dying. RICCARDO: Yeah, it's a great deal. Like it's a, It's a great deal for them. I mean they. And that's, and that's where I scratch my head. I didn't realize because I don't. I never focus on the strike price because that's not something I understand of stuff I worry myself with. But yeah, when I hear oh, inkling is such a bad deal, it's like, are you sure? Such a bad deal for the taxpayers. Maybe it was a bad. I mean it's a bad deal in the sense that was it really necessary to transfer the risk? But like as I wonder what, what the strike price would be if ADF wasn't absorbing all of the losses. What would that look like? Chris: £250. Who knows, right? It could be very high. Could be very high. So I think the way that I'd interpreted this move to um. And we're going to talk about how size we'll see as being financed with regulated asset base. For me, I was like, okay, this is just the Brits. They've been burned. They've recognized that they can borrow using sovereign debt at a much lower rate. Something like two thirds of the final cost of electricity from Hinkley Point is. Is finance cost. I think that doesn't include the overruns essentially because if the strike price was there in advance, it's probably even higher. Uh, sorry, the amount of. Interesting to know what the overnight construction cost and the, the uh, tic that the total cost would be a total installed cost, what that would be like. Um, if you had access to the French books there. But in any case, I was thinking size we'll see was being pushed more by the Brits to say, hey, we can borrow cost cheaper. We're going to, you know, not make this all a private equity play, but we're going to, you know, harness our ability to borrow cheaply. But in looking at it this more it seems like it's equally. The uh, French would have a similar be advocating for the model that we see at size we'll see as well saying, hey, listen, you know, we'll take a 12% equity stake but you know, we don't want to have what happens at Hinkley happen again. RICCARDO: Again. Uh, you know, I've always, I've unpacked like the French. Chris: The French wouldn't have signed back up for another, um. Hinckley. RICCARDO: No, I mean the interesting part, the interesting part is that, you know, probably when. So we're talking what, 2019, 2020. Because I think the funding competition for size, well was 2023 reach for an investment decision in 24. So I think, I think it's. Yeah, the UK government wanted to do another inclima. Maybe they didn't m. Because they had a lot of political backlash on the strike price. Right. That's what. You know, I think you just proved to me that that was this public sentiment, the strike price is too high. But that was like six, seven years ago when the cost of Iran's were not known. Chris: So all people knew, okay. RICCARDO: All people knew was like, it's a high strike price. Ah. So the UK government was motivated not to replicate Inkly, but at a certain point EDF said we are not replicating Inkly. We're not going to do that again. We're not going to put our balance sheet on the table. We are not going to eat all the losses. Like, we're not doing that again. But from what I gather from my research is that the UK government did try to have uh, a uh, do over of Inkly and surprise, surprise, nobody showed up. And so they realized that they needed something different and they had this model in the uk. I mean they're regulated as a base they use for size. Well, is actually the regulated asset based model that was used for Thames Tidal, uh, Thames Tuttle tunnel, which is a, is a massive sewage tunnel in London that is basically a supposed. Currently the sewage overflow goes into the Thames. It used to overflow all the time. Uh, and so they needed to stop that. So they needed to build a brand new tunnel to capture all the overflows because it was happening too often. And so again tunneling is probably similar as nuclear. Like, uh, you know, it's very risky, very unpredictable. You just can't tell what the ground is going to look like when you start digging. And so nobody was going to give a fixed price for that tunnel. Um, and so back in the, in the early 2000 or mid 2000, the UK government came up with, well, they tried and then they failed. So then, then they had to really stitch together a way of doing it that would allow with our private capital. And they're basically the RAB model for Thames title. They literally lifted and shifted it into, into size. We'll see. So it's not actually novel what they've done on size. Well, is not novel at all. It's novel because it's in the nuclear industry and when you look at the water sector in the uk it's deregulated. Right. You have all these private company operating. And that was the other problem. No, you know, no private company operator would absorb such a big capital cost. They just don't have the balance sheet. These are like uh, or they operate in entity, they operate infrastructure that was built over the last 150 years but they don't have the capital to actually build these massive assets. So they had to come up with a different model if they wanted to keep the deregulated environment. Chris: The other thing I understand is people say this regulated asset base is such an interesting novel concept. You've demonstrated that it's not. It comes over from a different sector. But, but I mean this is what regulated monopoly utilities have done since the time of Memorial, to my understanding, or what happened at VC Summer and Vogel. There was construction work in progress. And essentially the brilliance of the model is that you can charge the rate payer before um, you actually generate electricity and you can start paying back some of the debt, uh, charges that are being incurred. Is that correct? RICCARDO: Yeah, I mean again that was, I think, uh, you know, think of the money that were the equity was invested. La Case is the money manager of the pensioners of Quebec. Right. So they don't have a humongous risk appetite because they don't want to lose the pension's money and also they need to generate profit in order to keep paying those pensions. Right. So there's no way that, that a pension fund can go 10 years without receiving any payment construction. But by the way, again, nothing novel and I was actually shocked to find out that Ontario has done the same thing two years ago. It's not to the extent of size, well not to the extent of the uk but you know the Ontario government, I can't remember the act, but there's an act and they introduced concurrent cost recovery recovery which is uh, allows opg because in Ontario, Ontario is a regulated asset based model and in the legislation did not allow OPG to recover anything until you start producing electricity. Chris: Yes, yeah. RICCARDO: However the concurrent cost recovery that was developed for the new build, so the NMP allows for recovery of interest during construction and in fact this, you know, um, for the Canadian or the Torontonian. There's an article in the Star from January when OPG started, started charging for, for this interest. You know, the Star picked it up and it was, I don't think he went anywhere got any traction, but it was certainly noticed and, and reported that OPG was getting money before producing electricity. You know, and so yes you can if you wanted the headline that, oh my God, why, how they're allowed to do that, why they're doing that. But on the other hand, and that's a mechanism to keep the cost of electricity down because there is no benefit of paying interest on interest. And by the way, the way the Ontario done it is quite sensible because it's only the interest. So what you don't want is interest on interest. So if you're actually recovering the interest during construction, you're not paying interest on that interest. So there's no capital being repaid, there's no profit it taken out of the project before the project is complete. So Ontario is a bit more delicate size, well is be more, you know, you're taking a pound sterling from each consumer and that money is then used to provide the profit, the yearly profit that the equity investor requires. And to be fair though, it's not that bold. I think they're, they're supposed to get a 12% return on their investment during the construction period. You only get 6% return and the other 6% is paid as a balloon payment once you reach COD. Chris: So just getting back to this idea again of whether we should finance things, um, using public debt versus trying to get things off of the public books, um, put some risk onto the private sector. The criticism certainly, I think when it comes to things like hospitals, um, roads, bridges, other things like that is eventually the public catches up. If the project fails catastrophically, usually the state's going to jump in and save it. Um, so ultimately the risk is really not with the private actor. And in the end, you know, if you account for it in 30 years time, you've paid more. I think in most cases again, in terms of total amount of capital spent at uh, Hinkley. Yes. In terms of what the UK has had to spend, I guess not so much given insane crossover runs that have made that strike price that was once controversial look fairly attractive. But am I getting that right in terms of this? I have a tendency, you know, just politically I guess, to favor this idea of like, yeah, the public should bore at low interest rates, um, and that's how we should finance these big projects. They are public interest, uh, bits of infrastructure, um, that make life better for everybody. And it's not something that we need to look at purely from a sort of quick return on investment business, uh, cases as the private sector might have. But it has been, you know, a little eye opening to, to again understand some of the nuance in terms of, um, how people, how people are taking risk. But yeah, that, that's criticism in terms of. You mentioned that there's been a turn, I think, away from, from this, you know, PFI model, or there's less, I guess, of these public private partnerships. Um, what was that based upon? What's, what's the experience been? RICCARDO: I think, you know, the premise of private capital was, you know, transfer the risk and you're going to get better outcomes. Leave it to the private sector and the private sector will generate better outcomes. And I think what is being demonstrated is that ppp, pfi, they don't always generate better outcomes and in fact sometimes they don't generate good, uh, outcomes at all. And so there's been a rethink based on that fact. And I don't think you have to look very far. You know, there's lots of projects in Ontario that were delayed where there were PPPs. And so the premise that the private sector can do it better and the private sector will generate better outcomes, that premise is no longer valid because evidence tells you otherwise. So then why are you paying a premium to get private capital if the benefit that private capital bring is actually not there? Chris: I guess one reason is because you can sort of kick it down the road. The total cost is higher, but you're paying that in sort of yearly installments rather than having to borrow a bunch of money up front. Is that one of the reasons? Obviously there's a political angle, you know, as you mentioned, you know, when reporters get a hold of stories and it's a big number, it doesn't look good for the government, but yeah. Is it that ability to sort of amortize the cost even though the total cost is more? Can that not make sense from a time value of money perspective? RICCARDO: Yes and no. Because from an account, I know now we're getting really, really technical, even beyond my expertise, but like, you know, there's a difference between accounting and financing, right? So just because you're borrowing the money and so the government doesn't have to borrow it, but from an accounting standpoint, that money, that liability is recorded. So even though we're building, let's say we're building our hospitals and we're borrowing the money to fund the Construction because the hospital is still on public land and it still belongs. The ownership of the hospital is with the province. From an accounting standpoint, even though somebody else is borrowing money, you have to recognize that liability. So it's on your books. So it does constrain you. So it's not that simple that you can just kick uh, down the car. It gets a bit more complex than that. But certainly politicians use that, that because it's so technical that you can get away by saying, saying that you can get away, that you can demonstrate value. But the other point with private financing is, is that you basically again, it goes, it goes to. Not all entities have the capabilities. Right? So we were lucky enough that OPG has been building power plants for the forever and they build nuclear power plant, normal power plant. So they are an experienced owner. Right. But that's not the case everywhere. Right. There are other, you know, if somebody wants to build a new nuclear project, they might not know how to go about it. So actually having the private sector with more skin in the game, it's beneficial. Right? So it really depends. It really depends who the owner is, who the parties involved in the transactions are. Because you know, if you're building a new nuclear power plant in the Philippines, I mean there's very little experience there. So they do want the private sector, the opera. They don't have an equivalent of OPG with tons of experience. And same with hospitals, right. I mean I know contractors that gone and built hospital in the Caribbean. Right. I mean they need the private sector. They just don't have the expertise. They don't have the know how. So they uh, they need to pay more to, to buy the expertise and to transfer some of the risk because they don't know how to manage that risk. So it really, it depends, it depends on the jurisdiction, I guess. Chris: Just one more, one more sort of question to clarify here because it seems to me the private sector was not terribly motivated to take on a lot of risk. And to be like we mentioned that EDF and cgn, the Chinese nuclear corporation or group are not your typical private equity entities. Um, they're essentially public companies for, for all means purposes. So is that like, were those exceptions in terms of being able to or being willing to take on such an extraordinary amount of risk? Is that unique to these particular examples? Um, in general, you know, in these arrangements there's, there's not that same tolerance or if it was an entity unlike edf, they would have just had a strike price that was just so ridiculous to yeah. RICCARDO: Account for the Risk, you know, I mean you talk about, but even Rosa Tom, I mean if you look at all the oem, right? I mean, I mean apart from Can Do, Westinghouse, I mean they're all, they're all government backed, right? Rosa Tom is going back. And, and so that's the difference, right? And so they have, you know, you have different structure and you, you have previous guests, right? I mean the government of Canada used to, to market the, the can do technology. So then you add, again, you have a state, you add a state backed product. We can do. But then in 2011, 2012, whenever it was, it was trying, the IP was, the commercialization of the IP was transferred, then you lost that coming back. And the same happened to, to, I don't know the full history of Westinghouse. But you know, they certainly ended up where we are in terms of can do in terms of their, the way that they are financially structured. Uh, it occurred to me, like Atkins Realis is a portfolio company of LA Case. So we sit in a fund of LA Case, Westinghouse sits in a fund of Brookfield. So we're not that dissimilar from a commercial standpoint. Very different from a technology standpoint, but from a commercial standpoint we're actually very similar and we're very different from edf, which is state, Rosatron, which is state backed. Even the Korean are state backed. So they can, they can do different things that you know, a Westinghouse or uh, can do, cannot do. Chris: So what do you envisage? Um, let's say that the smart darlington goes reasonably well and there's appetite to do large nuclear power. We're talking, I think realistically, um, if we're talking about, you know, four to eight large reactors, we're in the high 100 billion plus sort of set of numbers there. So how do you envisage that getting financed? I was just looking at some numbers like the GDP of Ontario is about 1.2 trillion a year. I think our debt is about half a trillion. Gross debt. I'm not sure what our annualized debt is. There's a limit to how much debt the public sector can take on before. I mean, I'm at the edge of my knowledge base here, but before, I don't know if the bonds become too pricey or the cost of servicing debt becomes too much. So what do you think? If you had to have your crystal ball in front of you, how, uh, how do you think it's going to go? How would you advise it to go? Um, obviously, as you Mentioned there's Case Deepo, which has some relationship with Atkins Realis, there's Brookfield, that has some relation with Westinghouse. There's pension funds that could have, could have an interest or what do you think that structure could be or should be? RICCARDO: Yeah, look, if it becomes a capacity issue, like a liquidity issue, so uh, actually coming up with a physical cash, you know, I think you might want to tap into the private sector, but you've got to do it in a way that you don't increase the cost of that you keep the cost of capital low. And by the way, the other problem with financing, being a civil engineer, I was shocked when I learned that, you know, it's lowest cost, lower, lower common denominator. Right. So, so when you're getting with this large project and you need to finance it, uh, you need to attract all sorts of type capital. And so you have people with a higher risk appetite than others. And so you know, they might give you a lower, a lower rate, but because you're pooling all these entities together, the most expensive capital, it determines what everybody else can charge. So the, the more investor you, you have to bring in, into in order to meet your capital demands, the more likely is that your cost of debt is going to raise because it's always going to be the last person that comes in with the highest cost is going to raise everybody else. Right. Chris: It's like a most favorite nation sort of. RICCARDO: Yes. So, so I don't know that there's, there's really uh, uh, uh, I think when, when you, when I research size will see. I mean it took them years, it took them years of negotiation and they, they, they ended up where they ended up. That's not where they start. Where they ended up is not where they started. They had a significantly different transaction, probably resembling more Hinckley, even though the Inkley was on the table. But they probably started with, you know, a small variant of Inkley and then through negotiation they got where they, they got. But I believe that the UK government was, ended up where they ended up kicking and screaming. Right. They wanted to transfer a bit more risk, but they, they couldn't. Uh, they would have walked away or would have cost too much. Chris: So I mean in the case of the technologies available in Ontario, we've can do, we have Westinghouse. You know, I think the Koreans have uh, bowed out. Um, EDF has retreated to I think trying to build six reactors in France. They're, they're you know, not having a huge appetite to export, uh, EPR2s now I believe. So in that case we don't have a source of private capital that's willing to take on extraordinary. The Brookfield is no, uh, edf, ah, shall we say they don't have the same kind of appetites. So what does that mean for the cost of capital? I mean it seems to me like it's quite a different arrangement. EDF is coming in as, as the constructor, as the equity partner, as the financier. That's a very different relationship in terms of a private source of capital to a private equity fund like Brookfield. RICCARDO: Well, I think Ontario is uniquely placed because of the experience. Right. And even if you look at uh, if you look at the SMR that has been built now, you've got a civil contractor, you've got a technology provider, but ultimately OPG is wrapping all that risk. And they are very experienced and knowledge, very experienced and knowledgeable owner. So they are able to take two separate entities, so the civil contractor and technology contractor, and bring them together and manage that interface risk. You know, when you talking to EDF or talking to uh, the Korean, they might be able to actually do that themselves. And that's why they're successful in jurisdiction where there isn't an experienced owner. So they can say, we're going to take care of the interfaces. Don't worry, we'll deliver it for you. I think Ontario is uniquely placed that uh, we have a long history and experience. I don't have the answer for you. What is going to happen to the balance sheet capacity of the profits of Ontario? Where is the hundred billion dollars going to come from so far with the Chris: smr, this is OPG lending. It's backed by the Ontario, uh, government. And there's the, I think the Canada Growth Fund, there's some federal investment, but yeah, it's all, essentially, it's all public, it's all low cost, public debt. And I guess the question is, do you foresee there being a similar arrangement with, you know, $100 billion to fund large nuclear program? Um, or do you think we have to bring in the private sector? And if we do, how much more expensive is that going to be given that it's not going to be EDF or China nuclear group of fronting the coin? RICCARDO: I think if there is a capacity construct, capital capacity is constrained. You will have to bring private capital, but you will have to do it in a way where you keep the cost down. And so you're going to have to look at size. Well, where, you know, when you look at Size. Well, at the end of the day, you know, we didn't talk too much about it, but the majority of the capital size was public. Right. So I think it's uh, 36 billion from the UK wealth fund, if I'm not mistaken, or 30 billion, uh, pounds from the UK wealth fund. The equity is split 45% UK government and the rest is the private sector. So it's really a sliver of private capital. And the reason being, and I believe the reason. And so the intent is also to refinance. So you basically the UK government wants out eventually. So they, they're not going to be, uh, they're going to be there for the next 60 years. They, once the plant is de risked, I start producing electricity, there's going to be a massive refinancing where their, their debt is going to be refinanced. So, uh, commercial institution will come in because at that point the construction risk is gone and that nuclear construction risk is gone. Chris: Just printing money for six now. RICCARDO: Now it's fine right now. Now lenders know how to take that operating risk of a nuclear power plant. So the UK government will exit and, and, and maybe make even some money out of that exit. And they're going to exit both, I'm assuming both the equity and the debt. So they're really bridging, you know, they're stepping in, they're bridging a situation where nobody else wants to come in, but they don't. They're not going to be there forever. It's going to refinance and then, and then there's going to be financial, engineering and financial activities that happen during operation. And, and I'm, you know, will the UK government be, you know, net positive at the end of it? Probably not. But uh, ultimately the, the social benefit is that they now have a nuclear power plant with a lower cost of capital, with a lower cost of electricity because they stepped in and they money and they're taking care of the, or the construction period. Chris: Do you have any sense of how, um, much less the uh, cost of capital will be on size? Well, C versus Hinkley. RICCARDO: Uh, C. Uh, no, but it can be calculated. I haven't done it, but it is. There's a lot of public information out there. Chris: I've heard numbers like it's, you know, 40, 50% cheaper in terms of the financing cost. RICCARDO: Yeah, it doesn't, it doesn't surprise me. Yes. Because that interest compounds. Right, the interest compounds. And if it's a high cost of capital, it compounds at a higher cost Chris: yeah, it's just, uh, it's because it's across jurisdictions, um, and it's the French that are incurring so much of the cost, it becomes hard to sort of get your head around. Or my head around, anyway. Well, Riccardo, I've, uh, learned a lot starting, uh, from a pretty extraordinarily junior level here, so thank you for, uh, helping demystify the topic a little bit. RICCARDO: My pleasure. And I hope I didn't. I didn't make it too complex. I mean, I can get carried away, but I really enjoyed this, uh, conversation. That's it for this episode of Navigating Major Programs. If you enjoyed the conversation, please follow the show and consider leaving a review. To continue elevating the conversation, join us on navigating major programs LinkedIn page. I'm Riccardo alongside Shomila Chatterjee and Evgenia Jelena. Thank you for listening.