Herbert Smith Freehills Kramer Podcasts · Herbert Smith Freehills Kramer Podcasts
Delay claims are among the most common and most contested in construction disputes, yet the underlying concepts are frequently misunderstood or misapplied. In Episode 2, Noe Minamikata and Xavier Milne simplify the meaning of delay in a construction context, "float", as well as extensions of time, and the importance of procedural compliance when making claims. Essential listening for employers and contractors alike.
0:11Noe MinamikataWelcome to another episode of the Construction Law Shortcast series where we'll be deconstructing fundamental principles of English construction law.
0:19Noe MinamikataAll in just five minutes or thereabouts.
0:22Noe MinamikataI'm Noe Minamikata from the London Construction and Infrastructure Disputes Team here at HSF Kramer.
0:29Xavier MilneAnd I'm Xavier Milne, also from HSF Kramer's London Construction and Infrastructure Disputes Team.
0:36Noe MinamikataIn this episode, we'll be focusing on three related concepts which frequently come up in construction disputes.
0:43Noe MinamikataDelay, float, and extensions of time.
0:46Noe MinamikataTo start us off, Xavier, can you walk us through the concept of delay and what it means in a construction context?
0:53Xavier MilneSure.
0:54Xavier MilneUnder most construction contracts, the contractor needs to complete the works by a fixed date specified in the contract.
1:02Xavier MilneThis is often referred to as a scheduled completion date.
1:07Xavier MilneWhen we talk about delay in a construction context, what we usually mean is delay that impacts the scheduled completion date.
1:15Xavier MilneThis is known as critical delay, because it involves delay to the critical path to completion.
1:23Noe MinamikataSo if the contractor's progress is delayed but the scheduled completion date isn't impacted, this doesn't qualify as critical delay, is that right?
1:32Xavier MilneThat's right.
1:33Xavier MilneMost construction contracts also contain, or should contain, a mechanism for addressing critical delay.