The Construction Law Shortcast: EP1 The prevention principle and time at large

What happens when an employer's own conduct prevents the contractor from meeting the contractual completion date? And what are the consequences when a contract has no effective mechanism to deal with acts of prevention? In the first episode of the Construction Law Shortcast, Xavier Milne and Noe Minamikata tackle two foundational principles of English construction law that anyone involved in construction projects needs to understand: the prevention principle and time at large. These concepts have significant practical implications for the completion date, liquidated damages regime, and other contractual relief potentially available to the parties. A concise breakdown of two principles that neither employers nor contractors should overlook.

Oct 222026
6 minlength
40transcript lines
Publishertranscript source

Transcript first 15 of 40 lines

0:12Noe MinamikataWelcome to the Construction Law Shortcast series where HSL Kramer's London Construction and Infrastructure Disputes team will be deconstructing fundamental principles of English construction law, all in just five minutes or thereabouts.

0:26Noe MinamikataI'm Noe Minamikata, Knowledge Council from the London Construction and Infrastructure Disputes Team.

0:33Xavier MilneAnd I'm Xavier Milne, Senior Associate, also from the London Construction and Infrastructure Disputes Team.

0:41Noe MinamikataIn our very first episode, we'll be focusing on two essential principles that underpin modern construction law, the prevention principle and time at large.

0:52Noe MinamikataSo, Xavier, can you start us off by explaining what the prevention principle is and why it's so important in the context of construction contracts?

1:03Xavier MilneWell, it's often overcomplicated, but put very simply, the prevention principle is a rule that a party cannot insist on the performance of an obligation which it has prevented the other party from performing.

1:18Xavier MilneIt's not a construction-specific principle, but it is one that the parties to construction contracts need to be particularly alive to.

1:27Noe MinamikataAnd why exactly is that?

1:30Xavier MilneWell, for example, if the employer somehow interferes with the contractor's contractual rights and causes delay that stops it from finishing on time, the general rule is that the employer won't be able to hold the contractor to the original contractual completion date.

1:52Noe MinamikataOkay, and in those circumstances, how do the parties determine when completion needs to occur, if not by the original completion date?

2:02Xavier MilneNormally, the contract will have a mechanism allowing the employer to reset the completion date where there's been an act of prevention, where it doesn't, or where there is an event that isn't captured by the mechanism, then time is said to be set at large.

2:20Xavier MilneThis means that the contractor's original obligation to complete by a specified date is replaced by a lesser obligation to complete the works within a reasonable time.

2:33Noe MinamikataAnd how would you determine what constitutes a reasonable time?

2:39Xavier MilneYou could probably dedicate an entire shortcast on that topic.

2:44Xavier MilneBut essentially, it'll be a question of fact and assessed by means of a broad consideration of what would, in all circumstances, have been a reasonable time for performance based on the contract in question.