Energy Future: Powering Tomorrow’s Cleaner World artwork

Energy Future: Powering Tomorrow’s Cleaner World · Peter Kelly-Detwiler

PJM’s New IRAS Filing: How Grid Operators Plan to Regulate Large Data Center Loads

In this episode, I break down PJM's recent filing to the Federal Energy Regulatory Commission (FERC) for an Interim Resource Adequacy Service (IRAS) . As massive new data center loads exert a tremendous pull on grid reliability, power quality, and energy prices, this interim proposal represents a major new regulatory mechanism to manage large electrical loads . Here are the key details from the proposal that I analyze in this video: The Scale of the Problem: Out of 32 gigawatts of forecasted demand growth in PJM between 2024 and 2030, a massive 30 gigawatts of that growth is driven by data centers . What is IRAS? PJM’s proposed Interim Resource Adequacy Service focuses specifically on new Large Load customers (primarily data centers) that do not provide their own power supply . The Emergency Shedding Protocol: Under IRAS, during periods of high grid stress, PJM would initiate an emergency notification procedure . This signals utilities to reduce or transfer the electricity demand of these new large loads before calling on standard demand response resources or proceeding to rotating blackouts . The "Build, Bring, or Buy" Standard: Large loads that do not bring new capacity or cover their demand through the upcoming Reliability Backstop Procurement will be subject to IRAS . This matches the White House Ratepayer Protection Pledge to "build, bring, or buy" the generation resources needed to satisfy new energy demands . The Large Load Registry: PJM plans to maintain a registry to track large loads and furnish information to state regulators and utilities . This allows state-level entities to manage retail load reduction and cost allocation while PJM retains the tools needed to handle grid reliability . Emergency Demand Reductions: If utilities do not acquire capacity equal to or above the combined peak demand of these new large loads, PJM would direct those specific zones to reduce demand proportionally during emergencies . Large loads may also waive compensation for cutting demand to protect ratepayers from rising bills . The 2029/2030 Capacity Auction Shift: Starting in December with the 2029/2030 base residual capacity auctions, new large loads that arrive without the necessary power supply won't be included as demand when future power needs are calculated . The Ratepayer Cost Impact: Over the last four capacity auctions (mid-2025 to mid-2029), PJM's capacity charges totaled over $63 billion . The Independent Market Monitor calculated that data loads drove up capacity costs by $29.4 billion—accounting for approximately 46% of total capacity payments . Most of these data loads are currently only projected rather than actually built . This December's auction results will give us a clear look at how data loads continue to impact ratepayer costs . If you find this analysis of grid reliability and energy regulation helpful, please like, subscribe, and leave a comment with your thoughts on how your region is handling data center load growth. Support...

Aug 272026
5 minlength
36transcript lines
Publishertranscript source

Transcript first 15 of 36 lines

0:03SPEAKER_00I keep wanting to escape from the latest grid operator proposals addressing large loads, but it's like I'm helplessly ensnared in that tractor beam from Star Trek.

0:11SPEAKER_00I simply cannot get away.

0:13SPEAKER_00That's because, to just hopelessly overuse this analogy, the gravitational exertion of these massive new loads on the grid is tremendous, seemingly affecting everything around it, such as power quality, energy prices, capacity auction results, and overall grid reliability.

0:30SPEAKER_00So this week we're going back to PGM, which just came out with a plan submitted to the Federal Energy Regulatory Commission, the FERC, called the Interim Resource Adequacy Service, or IRAS.

0:42SPEAKER_00It asked the FERC to accept the petition within 60 days.

0:46SPEAKER_00Uh-oh, I see the word interim, and I immediately get the sense this will be some kind of measure that was stapled on top of something else, which it kind of is.

0:55SPEAKER_00So let's dig in to understand what it means and some of the key provisions.

1:00SPEAKER_00IRAS is intended to address new large load customers, read data centers.

1:04SPEAKER_00In fact, the grid operator comments in its filing that of the 32 gigawatts of growth forecasted in PGM's future demand between 2024 and 2030, 30 gigawatts of that is attributed to data centers.

1:19SPEAKER_00PGM focuses on these data centers that don't provide their own supply in the IRAS.

1:24SPEAKER_00When the grid is highly stressed and ready to call on demand response resources to shed load or go even further into other emergency responses such as rotating blackouts, PGM would institute an emergency notification procedure signaling utilities to reduce or transfer large load electricity demand from these new large load customers.

1:45SPEAKER_00The large loads that haven't developed their own new capacity or haven't covered their demand through the reliability backstop procurement, another special process starting this fall, will they be subject to IRAS?

1:57SPEAKER_00All large loads would be tracked through a PGM-maintained large load registry that would also register existing large loads, and that would furnish relevant information to states, utilities, and relevant regulatory agencies so they can apply the IRAS service to large load customers if they desire.

2:14SPEAKER_00PGM notes that the IRAS proposal is designed to play nice with state authorities, allowing state-level entities to oversee and manage established and regulated retail load reduction plans and retail cost allocation.

2:27SPEAKER_00At the same time, PGM would retain the tools needed to maintain critical grid reliability.

More Energy Future: Powering Tomorrow’s Cleaner World episodes →