Energy Future: Powering Tomorrow’s Cleaner World · Peter Kelly-Detwiler
The unprecedented rise of AI and massive data centers is putting severe strain on the electric grid, prompting a major regulatory crackdown . Large loads pose a unique threat because they are huge (sometimes requiring gigawatts of power), desperate for quick interconnection, and highly unpredictable due to the prevalence of "phantom loads"—projected facilities that sit in interconnection queues but may never actually be built . Furthermore, these large language model operations can physically destabilize the grid by interfering with the 60-hertz sine wave and abruptly snapping offline during minor power quality fluctuations, which has already caused over-frequency events . To bring order to this chaotic "land rush" for power, the Federal Energy Regulatory Commission (FERC) has issued a show cause order under Section 206 of the Federal Power Act . The directive targets six major regional grid operators: PJM, MISO, SPP, CAISO, ISO-NE, and NYISO . Finding that current tariffs are likely "unjust and unreasonable," FERC is demanding that grid operators either justify their existing rules or file reforms within 60 days . FERC requires the grid operators to address five specific categories of reform: Developing more efficient transmission study processes and evaluating Grid Enhancing Technologies (GETs) to maximize existing grid capacity without waiting for multi-year physical upgrades . Providing greater cost transparency to ensure the massive infrastructure costs of these upgrades are not unfairly shifted to everyday ratepayers . Accommodating co-location agreements, establishing clear procedures for data centers that bypass traditional grids to build directly next to power plants . Creating new transmission services for flexible loads that can throttle their operations or switch to onsite batteries to support grid reliability . Developing a transparent process to study how local grid stability is impacted when massive new loads are placed close to existing generation assets . In addition to the 60-day reform deadline, the grid operators have just 30 days to submit a detailed report outlining how they will ensure sufficient generation exists to serve both everyday users and these massive new data centers . Ultimately, the mandate is designed to force grid planners to look at best practices across the country and implement rigorous rules so that existing ratepayers do not get hurt by the rapid expansion of AI technologies Support the show 🎙️ About Energy Future: Powering Tomorrow’s Cleaner World Hosted by Peter Kelly-Detwiler, Energy Future explores the trends, technologies, and policies driving the global clean-energy transition — from the U.S. grid and renewable markets to advanced nuclear, fusion, and EV innovation. 💡 Stay Connected Subscribe wherever you listen — including Spotify, Apple Podcasts, Amazon Music, and YouTube. 🌎 Learn More Visit peterkellydetwiler.com for weekly market insights, in-depth articles, and energy analysis.
0:03SPEAKER_00A couple weeks ago, I dragged you down the regulatory rabbit hole of Urkhart's Batch Zero interconnection process for large loads.
0:09SPEAKER_00Then I gave you a regulatory reprieve with a light discussion on sodium batteries, but today we're going down another regulatory borrow.
0:16SPEAKER_00And again, this is related to large loads, aka data centers.
0:21SPEAKER_00Too bad, but it's got to be done.
0:22SPEAKER_00We'll be looking at the Federal Energy Regulatory Commission's FERCS show cause order under Section 206 of the Federal Power Act to each of the six regional grid operators under its jurisdiction, which directs them to justify or reform rules governing how data centers, manufacturing facilities, and other large energy users connect to the electric grid.
0:42SPEAKER_00Well, if you can get past your gleeful anticipation, let's jump in and first let's set the stage.
0:47SPEAKER_00Unless you've been under the proverbial rock for the past couple of years, you know that large loads, mostly data centers, are posing unprecedented challenges to many utilities and grid planners simply because they're A, huge, up to several gigawatts in some instances, or even more.
1:03SPEAKER_00B, desperate to connect to the grid with at least one estimate that advancing a gigawatt of load by a year is worth about$7 billion in revenues, and C, characterized by a high degree of uncertainty as to whether or not all these projected loads will come to fruition.
1:18SPEAKER_00So-called phantom loads, projects that may never be built, but they're in forecasts or interconnection queues, could be as much as 3 to 10x the actual number of projects that eventually find their way into the ground.
1:31SPEAKER_00Another issue, let's just discuss briefly, some of these data centers can be potentially highly destabilizing to the grid in two ways.
1:38SPEAKER_00First, because of the way chips process data in the large language models, they can really mess with a 60 hertz sine wave we all love, the so-called harmonics.
1:46SPEAKER_00And second, because if there are issues with power quality, like frequency and voltage, data loads can instantaneously come offline to protect their equipment and go to backup power.
1:56SPEAKER_00In Dominion, a couple of years ago, a failed lightning strike arrest or led to 1,500 megawatts of load snapping instantaneously off the system, resulting in an overfrequency event that jeopardized the grid.
2:07SPEAKER_00It's happened since then both there and multiple times in Texas, and the North American Electrical Reliability Corporation, NURC, recently issued a rare level three warning about this and discussed the need for ride-through capabilities to be created.
2:21SPEAKER_00Okay, so all this stuff is messy and detail laden, but assume you're still with me, let's get into the FERC show cause orders related to the grid and specifically to interconnections.