In this week's episode, we explore a tale of two very different eastern power grids: PJM and ISO New England. For years, PJM's interconnection queue was hopelessly snarled, with the grid operator getting overwhelmed by small renewable projects and speculative developers. Project reviews were taking five to seven years under a "first-come, first-served" model, leading to massive delays and withdrawn projects. Now, PJM has overhauled its process to a "first-ready, first-served" approach, requiring developers to provide meaningful upfront financial commitments and proof of site control. The results of their latest application window are staggering: PJM recently announced 220 gigawatts (220,000 MW) of proposed capacity across 811 new projects. Watch to learn more about: The new PJM fuel mix: Why gas-fired generation (106 GW) and battery storage (66 GW) are leading the queue, alongside a surprising 27 nuclear projects. Google's AI grid intervention: How PJM is deploying Tapestry’s HyperQ AI software to expedite the review of these massive data sets. The "Phantom Load" problem: Why speculative queue behavior is inflating capacity numbers for new data centers by an estimated 3 to 10 times. The supply chain reality check: Why much of this approved supply won't come online soon, as gas turbines are sold out through 2030 and projects like Commonwealth Fusion don't even have a working reactor yet. The New England contrast: Why ISO New England is facing the exact opposite scenario, having recently downgraded its load growth forecast to just 9% through 2035 due to a lack of data centers and slowing EV and heat pump sales. Finally, we discuss the unpredictable wildcards in grid forecasting. If the ongoing conflict in the Strait of Hormuz triggers an enormous petroleum price shock, New Englanders paying over $500 for 100 gallons of heating oil will race for heat pumps, instantly altering these long-term projections. In a world where everything is constantly in flux, the only thing grid planners can truly count on is the accelerating pace of change. Watch now to understand the regionally differentiated reality of our power grid! Support the show 🎙️ About Energy Future: Powering Tomorrow’s Cleaner World Hosted by Peter Kelly-Detwiler, Energy Future explores the trends, technologies, and policies driving the global clean-energy transition — from the U.S. grid and renewable markets to advanced nuclear, fusion, and EV innovation. 💡 Stay Connected Subscribe wherever you listen — including Spotify, Apple Podcasts, Amazon Music, and YouTube. 🌎 Learn More Visit peterkellydetwiler.com for weekly market insights, in-depth articles, and energy analysis.

May 142026
8 minlength
59transcript lines
Publishertranscript source

Transcript first 15 of 59 lines

0:02SPEAKER_00I've got your video for this, the first week of May 2026.

0:07SPEAKER_00Well, in late April, Mid-Atlantic Rid Operator PJAM announced that it finally overhauled its interconnection process with a redesigned approach aimed at improving the certainty, speed, and discipline of project review.

0:19SPEAKER_00For those of you who don't follow this at all, lucky you.

0:22SPEAKER_00The process of interconnecting new supplier projects involves getting in line, the queue, with a proposed project to be studied at multiple levels.

0:30SPEAKER_00These studies include the impact of a new project on existing power flows, whether or not new transmission infrastructure will be required, who pays for that, and the potential impact on neighboring systems.

0:42SPEAKER_00Queues have become hopelessly snarled in recent years, and not just in PGM.

0:46SPEAKER_00But for a while, PGM's review process took as long as five to seven years to get to a signed interconnection agreement.

0:53SPEAKER_00And at one point, the grid operator simply stopped taking new applicants.

0:57SPEAKER_00Delays were so long that almost three-quarters of the projects in the queues were withdrawn, including many that had achieved interconnection approval status, but had become uneconomical due to the lengthy time frames.

1:10SPEAKER_00A large part of the issue arose from the huge number of projects that caught planners by surprise.

1:15SPEAKER_00A decade or more ago, you had a much smaller number of larger projects, but as smaller solar, wind, and battery storage projects entered the picture in large numbers, PGM got overwhelmed by the sheer volume of cats and dogs and rats and frogs.

1:30SPEAKER_00There was also a lot of speculation in the mix.

1:33SPEAKER_00Developers might have a finite amount of capital to deploy in the U.S.

1:36SPEAKER_00while dealing with these clogged queues.

1:38SPEAKER_00So they might put different projects in various queues across the country, and if one got approved, they'd pull the others.