Energy Capital Podcast · Josh Rhodes & Matt Boms
Batch zero stops being theoretical on July 11. That is the day ERCOT’s rule for connecting large new customers takes effect. The new policy replaces a process that involved studying each giant load independently, then ordering restudies when new giant loads joined the queue, leaving projects stuck in a serial loop. Two prior episodes of this show traced how the new rule was designed. This one asks the people who connect the load what to fix before the next round. Already projects are sitting in the interconnection queue as new regulatory deadlines loom. ERCOT figures show more than 445 gigawatts of large loads in the process, and the rule sorts them into base load, studied load, and excluded load. Developers have until July 10 and July 24 to meet certain filing deadlines, and the full batch study is targeted for early April. The policy also shifts more of the analysis from individual utilities onto ERCOT. CenterPoint has been connecting large loads in Houston for decades. That experience drives a question the design phase mostly deferred: does a 75-megawatt cutoff for loads to participate in the program fit the manufacturing and industrial loads that move at the speed of business? On this episode of the Energy Capital Podcast, Joshua Rhodes talks with Caitlin Smith, chair of ERCOT’s Technical Advisory Committee and senior vice president at Jupiter Power, and Jason Ryan, executive vice president of regulatory services and government affairs at CenterPoint Energy. Smith walks through how stakeholders developed the rules on a compressed timeline. Ryan presses the forward question of whether the 75-megawatt threshold and an annual batch process fit the loads Houston routinely connects. Ryan’s concern is timing. When the batch becomes “the long pole in the tent,” he says, developers with real projects start to walk. The conversation works through: * WL-PUN and PCLR, the withdrawal-limited private-use-network and provisional controllable-load resource programs ERCOT is repurposing to fit more load onto the current grid. * The 75-megawatt cutoff, why Ryan questions whether mid-sized manufacturing loads belong in the batch at all, and the risk of projects sizing themselves at 74.9 to stay out. * Non-firm service and reliability, how a load that agrees to curtail differs from the century-old obligation to serve, and what testing CenterPoint needs before it trusts the switch. * What is permanent versus triage, which parts of batch zero survive into batch one and beyond as the Texas Legislature returns next year. New to the batch zero mini-series? Start with Eric Goff on how batch zero took shape and Tiffany Wu on the mechanics. How ERCOT sets the threshold and batch cadence will determine which loads get power on their own timeline and which wait for the next cycle. Timestamps: * 00:00 - Introductions: Caitlin Smith and Jason Ryan * 02:43 - What Batch Zero is and why ERCOT needs it now * 05:14 - Houston's diverse large loads, not just data centers *...
0:04SPEAKER_0Hey everyone, and welcome to another episode of the Energy Capital Podcast.
0:07I'm really excited today to have not one but two guests to talk about kind
0:12of what's going on in the ERCOT Batch Zero process and kind of how that may continue
0:17to play out.
0:18SPEAKER_0So today on the podcast, we've got Caitlin Smith.
0:21SPEAKER_0Caitlin has a BA in econ from University of Texas and a JD Law from Penn State.
0:26SPEAKER_0She's a policy consultant for CLEAResult for going on counsel at Jewell & Associates.
0:32She's a vice president of AB Power Advisors and is currently
0:35the Senior Vice President for Federal and Regulatory Affairs at Jupiter Power,
0:39one of the largest pure play energy storage companies in the US.
0:44But she also is the current chair of ERCOT's Technical Advisory Committee,
0:49the highest committee comprised of stakeholders,
0:51which makes recommendations to the ERCOT board.
0:54And that's going to really come in handy today as we talk about one of
0:56the biggest policy shifts that's working its way through the system.