Energy Capital Podcast · Josh Rhodes & Matt Boms
In ERCOT’s new interconnection process for large loads, a data center can connect sooner as a provisional controllable load resource. That is, ERCOT can curtail power above an agreed firm level. A study from Base Power and Piq Energy shows batteries near the transmission lines to a data center could stand in for most of that curtailment. In the study, 80 megawatts of batteries would clear every transmission constraint created by a 100 MW data center near Burleson, Texas, on Oncor’s system. A battery beside a strained line relieves it about one-for-one, while curtailing a more distant data center may relieve half as much. Any battery near the line has that edge. On this week’s Energy Capital Podcast, Joshua Rhodes talks with Chase Dowling, head of market operations for Austin battery company Base Power. The business model is Base Power retains ownership of the batteries it installs for retail customers, and homeowners subscribe to the service.Dowling puts the batteries’ reach at “80 percent, 85 percent of all of the constraints.” The rare failures that sever part of the system, he says, still need new transmission or generation. * The limits: the battery fleet needed grows faster than the load, and West Texas lacks enough homes for large fleets. No market yet pays batteries to act as transmission. * Who pays: Dowling proposes that a data center facing curtailment fund a battery fleet near its constraints, and the host homes get outage protection. * Utility fleets: for El Paso Electric and CoServ, Base builds co-branded fleets and hands control to the utility. It now installs in Chicago, in PJM. * Backup: Dowling says a portable generator can stretch a Base battery through a multi-day outage like Winter Storm Uri. Dowling says the challenge now is getting ERCOT to model these fleets at the transmission substation, where planners can see them. Chapters 00:00 – Chase Dowling and the new Base Power study01:01 – What Base Power has built since 202302:22 – Manufacturing home batteries as a grid resource05:10 – The homeowner value proposition07:50 – Base Core's generator port and extended backup11:43 – Deployment speed and what limits it14:43 – Regulated utilities and who controls the batteries16:28 – Lessons from Texas for PJM18:23 – Flexibility Without Curtailment: the paper's premise22:32 – Why location matters: 100 MW at Burleson Switch26:52 – How 80 MW of batteries hosts 100 MW of load28:47 – Bigger loads, the long tail, and the 80/20 rule35:13 – Batch Zero, curtailment risk, and who pays38:17 – Data center PR and how big this can get Resources People & Organizations * Joshua Rhodes (LinkedIn) * Energy Capital (Podcast - LinkedIn - YouTube) * Chase Dowling (LinkedIn) * Base Power Company (Website - LinkedIn - Base Core) Company & Industry News * Base Power raises another US$1 billion in Series D financing for US residential BESS * Base Power brings cheap batteries to residents in power-starved PJM * Base Power to launch 100-MW home battery...
0:04SPEAKER_01Hey everyone, and welcome back to another episode of the Energy Capital Podcast.
0:08SPEAKER_01I'm really excited to have Chase Dowling here from Base Power Company to talk
0:11SPEAKER_01about what the company's been doing,
0:12SPEAKER_01as well as a new study they've put out looking at the impact
0:16SPEAKER_01of distributed energy resources on the ability to unlock firm load
0:20SPEAKER_01for places like large loads, data centers.
0:23SPEAKER_01But yeah, really excited to have Chase here to talk about it.
0:26SPEAKER_01Chase has a PhD in electrical and computer engineering from UW, University of Washington.
0:32SPEAKER_01In and around there,
0:32SPEAKER_01he also worked 10 years at the Pacific Northwest National Lab,
0:35SPEAKER_01ending as a senior applied scientist,
0:38SPEAKER_01before switching over to machine learning at Tesla.
0:42SPEAKER_01Very recently,
0:43SPEAKER_01actually,
0:43SPEAKER_01as of recording this podcast,